R EQUEST FOR N EGOTIATED P ROCUREMENT

Please quote your public price, inclusive of taxes, FOB, Kalinga State University indicating the earliest possible time for delivery of the item(s) listed below, subject to the conditions and instructions set forth in the bidding documents of this request for negotiated purchases. Contract Name: Negotiated Procurement for the Construction of Performing Arts Theater at Bulanao Campus (Package Contract). Contract Location: Kalinga State University Main Campus, Purok 6, Bulanao, Tabuk City, Kalinga Approved Budget for the Contract: Php.

I NSTRUCTIONS TO B IDDERS

Unless otherwise specified in the BDS, the Bidder may subcontract parts of the Works to an extent acceptable to the procuring entity and specified in the BDS. In the event that a subcontractor is found by the procuring entity to be ineligible, subcontracting of such part of the works shall not be permitted. Statement of the bidder's SLCC corresponding to the contract to be bid in accordance with ITB clause 5.4.

Unless otherwise stated in the BDS, the financial part of the bid must contain the following: Any other document related to the financial component of the offer as specified in the BDS. one). Unless otherwise specified in the BDS, payment of the Contract Price shall be made in Philippine pesos.

The notice will be issued within seven (7) calendar days from the date of bid opening. When applicable, the BAC will conduct post-qualification of the bidder with the next lowest calculated bid.

B ID D ATA S HEET

1 Construction of Performing Arts Theater - Phase IV KSU-RAF-IB2016-05 2 Completion (of Phase V Construction) of Export. The name of the project is Negotiated Procurement for the Construction of Performing Arts Theater in Bulanao Campus (Package Contract). The minimum work experience requirements for key personnel on each project lot are as follows:.

Civil Engineer/Building Engineer 3 years 3 years Vocational/Registered Electrical Engineer 3 years 3 years Sanitary Engineer/Plumber 3 years 3 years Construction Safety and Health Officer 3 years 3 years. The appropriate notarized certificate of the construction safety and health program, points 1-7 of the above documents are prepared separately for the project sections. Duly signed Construction Safety and Health Program (approved by the Ministry of Labor and Employment).

G ENERAL C ONDITIONS OF C ONTRACT

The completion date is the date of completion of the works as certified by the Procuring Entity's Representative, in accordance with Clause 49 of the GCC. All materials and plants at the site will be considered the property of the Procuring Entity. The Contractor shall comply with all instructions of the Procuring Entity Representative that are consistent with the laws in force where the Location is located.

The performance guarantee remains valid until the issue of the certificate of final acceptance by the contracting authority. The contracting authority terminates this contract for default if any of the following conditions accompany its performance:. In the absence of the CPES assessment sheet, the contracting authority's existing performance monitoring system will be applied.

All drawings prepared by the contractor for the performance of the temporary works are subject to prior approval by the contracting authority's representative before being used. The approval of the contracting authority's representative does not diminish the responsibility of the contractor for the design of the temporary work. The Contractor shall obtain third party approval for the design of the Agency Work, if required by the Contracting Authority.

Each completed form will be verified and signed by the Representative of the Procuring Entity within two days of the completion of the work. Approval of the Work Program by the Procuring Entity's Representative will not change the Contractor's obligations. Either the Procuring Entity's Representative or the Contractor may require the other to attend a Management Conference.

Such payment request is verified and certified by the contracting authority's representative/project engineer. The contractor shall submit to the representative of the contracting authority monthly statements of the estimated value of the work performed less the previously certified cumulative amount. The contracting authority's representative checks the contractor's monthly statement and certifies the amount to be paid to the contractor.

S PECIAL C ONDITIONS OF C ONTRACT

NOTE: The duration of the contract is counted from the start date (NTP) and not from the effective date of the contract. The site is located at Kalinga State University Main Campus, National Highway, Purok 6, Bulanao, Tabuk Town, Kalinga and is identified on drawings no. The performance bond covers the period from the signing of the contract to the final acceptance. of the project by the government, whereby the warranty period as prescribed in sec.

For this reason, the coverage of the performance security shall include the defect liability period of one (1) year and shall not become due for release until the certificate of final acceptance is issued by the procuring entity. If there is no available site survey report prepared by the contracting authority, the bidder must conduct a site visit prior to the preparation of its bid. In the case of permanent structures such as Type 4 and 5 buildings as classified under the National Building Code of the Philippines and other structures made of steel, iron or concrete that comply with relevant construction regulations (e.g. DPWH Standard Specifications) such as but not limited to, steel/concrete bridges, flyovers, aircraft movement areas, harbors, dams, tunnels, filtration and treatment plants, sewage systems, power plants, transmission and communication towers, railway system and other similar permanent structures: Fifteen (15 years.

13 If the contractor is a joint venture: "All partners of the joint venture are jointly and severally liable to the contracting authority.".

S PECIFICATIONS

In this regard, the contractor or the key personnel to be assigned to him must have professional experience compatible with the undertaking as specified in point 12.1(b)(ii.2) of the tender information form. The contractor will, with the consent of the proponent, prepare any revised major changes/changes to the project during construction. The Contractor shall prepare weekly and monthly progress reports, supported by progress photographs and S-curves to monitor actual progress, to be used as the basis for progress billing to be submitted to the KSU Infrastructure Unit.

The contractor must fully address and comply with the final punch list to be issued by the KSU Infrastructure unit prior to turnover and acceptance of the completed project. The contractor must install electricity meter and water meter at their construction sites and must pay the actual amount for water and electricity based on their consumption at current rate. The Contractor shall clean the entire area by removing dirt, debris, paint stains, excess and spillage and shall leave the entire premises free of debris caused by their work to the satisfaction of KSU at no additional cost.

The contractor undertakes to pay any fees or charges due to any government agency or other duly established authority in connection with the construction project. He assumes responsibility therefor and the contractor is in particular liable for any responsibility arising therefrom. Above or equal to (15%) of the Contract Price less prepayment (Section 10.2), applicable withholding taxes and retention fund of ten percent (10%) of the Contract Price (Sec.

The work completion rate is assessed and evaluated by the KSU infrastructure unit. In the event of early termination, Contractor shall be notified by KSU within thirty (30) calendar days prior to such termination. SCOPE AND COVERAGE OF THE PROJECT WITH SPECIFICATION (See Scope of works per package on the next page).

PROJECT SCOPE AND COVERAGE WITH SPECIFICATION Lot 1: Construction of Performing Arts Theater - Phase IV.

D RAWINGS

B ILL OF Q UANTITIES

B IDDING F ORMS

  • G ENERAL
    • Scope of Bid
    • Source of Funds
    • Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices
    • Conflict of Interest
    • Eligible Bidders
    • Bidder’s Responsibilities
    • Origin of Goods and Services
    • Subcontracts
  • P REPARATION OF B IDS
    • Documents Comprising the Bid: Eligibility and Technical Components
    • Documents Comprising the Bid: Financial Component
    • Alternative Bids
    • Bid Prices
    • Bid Currencies
    • Format and Signing of Bids
    • Sealing and Marking of Bids
  • S UBMISSION AND O PENING OF B IDS
    • Deadline for Submission of Bids
    • Late Bids
    • Opening and Preliminary Examination of Bids
  • E VALUATION AND C OMPARISON OF B IDS
    • Process to be Confidential
    • Clarification of Bids
    • Detailed Evaluation and Comparison of Bids
    • Post Qualification
    • Reservation Clause
  • A WARD OF C ONTRACT
    • Contract Award
    • Signing of the Contract
    • Performance Security
    • Notice to Proceed
    • Protest Mechanism
    • Definitions
    • Interpretation
    • Governing Language and Law
    • Possession of Site
    • The Contractor’s Obligations
    • Performance Security
    • Subcontracting
    • Liquidated Damages
    • Site Investigation Reports
    • The Procuring Entity, Licenses and Permits
    • Contractor’s Risk and Warranty Security
    • Liability of the Contractor
    • Procuring Entity’s Risk
    • Insurance
    • Termination for Default of Contractor
    • Termination for Default of Procuring Entity
    • Termination for Other Causes
    • Procedures for Termination of Contracts
    • Force Majeure, Release From Performance
    • Resolution of Disputes
    • Suspension of Loan, Credit, Grant, or Appropriation
    • Procuring Entity’s Representative’s Decisions
    • Approval of Drawings and Temporary Works by the Procuring Entity’s
    • Acceleration and Delays Ordered by the Procuring Entity’s Representative
    • Extension of the Intended Completion Date
    • Right to Vary
    • Contractor's Right to Claim
    • Dayworks
    • Early Warning
    • Program of Work
    • Management Conferences
    • Bill of Quantities
    • Instructions, Inspections and Audits
    • Identifying Defects
    • Cost of Repairs
    • Correction of Defects
    • Uncorrected Defects
    • Advance Payment
    • Progress Payments
    • Payment Certificates
    • Retention
    • Variation Orders
    • Contract Completion
    • Suspension of Work
    • Payment on Termination
    • Extension of Contract Time
    • Price Adjustment
    • Completion
    • Taking Over
    • Operating and Maintenance Manuals

Our firm, including any subcontractor or supplier for any part of the Contract, is a national of the following eligible countries: [insert information];. Our firm, its subsidiaries or affiliates, including any subcontractors or suppliers for any part of the contract, have not been declared ineligible by the Funding Source;. h). We also certify/confirm that the undersigned is the duly authorized representative of the bidder and has been given full power and authority to do, execute and perform any and all acts necessary to participate, submit the bid and to sign and execute the following contract. for [Project Name] of [Procuring Entity Name]. k).

In consideration of the payments to be made by the Entity to the Contractor, as hereinafter mentioned, the Contractor hereby agrees with the Entity to carry out and complete the Works and to remedy any defects therein in accordance with the provisions of this Contract in all respects. Name of Bidder] authorizes the Head of the Procuring Entity or his duly authorized representative(s) to verify all the documents submitted;. If a partnership or cooperative: None of the officers and members of [Name of Bidder].

BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Bureau or the end-user unit, and the project consultants by blood relationship or affinity up to and including the third civil degree;. Declaration by the potential tenderer of all its current and completed government and private contracts within ten (10) years of the submission of the bid, whether or not they are similar in nature and complexity to the contract to be issued (SF-INFR- 15). Submitting a PCAB license with an expiration date after the bid opening date is grounds for disqualification of the prospective bidder (SF-INFR-09).

Duly notarized declarations of all potential joint venture partners pursuant to Section 23.1(b) of the IRR. Ensuring that the signatory is a duly authorized representative of the Bidder and has full authority and power to perform, execute and carry out any and all necessary actions and/or to represent the Bidder in the bid, with a duly notarized certificate from the Secretary confirming this. fact if the provider is a company, partnership, cooperative or joint venture". Note: The authorized representative must be the same designated employee of the contractor to transact business with the PCAB on behalf of the company.

Note: Any missing, incomplete or insufficient documents in the aforementioned checklist is a basis for complete rejection of the bid.

Mga Sanggunian

NAUUGNAY NA DOKUMENTO

“All BAC members shall be on a “jury duty” type of assignment until the Notice of Award is issued by the HOPE in order to complete the entire procurement process at the earliest